Three builders can price the same extension and return three totals that are impossible to compare at first glance. One may include drainage and painting; another may exclude both. A third may use low allowances for the kitchen, glazing or groundworks. Looking only at the total can hide the real cost and the decisions you will be asked to make after work starts.

The most useful comparison is a scope comparison. Give each builder the same plans and specification, ask for written clarifications, then line up the inclusions, exclusions, allowances and payment terms. The CCPC recommends multiple written quotes, recent references and clear written details of the price, work, timing and payment structure before a homeowner commits.[1]

This guide shows how to make that comparison for extensions, renovations and substantial repairs in Ireland. It includes a question list and a sample brief you can adapt before posting the job.

Give every builder the same information

Start with one dated package: drawings, schedule of work, room finishes, structural information already available, photographs and a short list of site constraints. Send the same revision to each bidder. If one builder identifies missing information, share the clarification with all of them. Otherwise you may accidentally reward a quote based on fewer assumptions.

  • Name the project and the exact property location at town or district level for the initial enquiry.
  • State whether drawings are concept plans, planning drawings or construction-level documents.
  • Include access, parking, occupied-home constraints, known damp or drainage problems and the desired programme.
  • Ask every builder to state assumptions, exclusions and any information they still need to firm up the price.

A site visit is especially important where the builder must assess the existing structure, access or ground conditions. An early budget estimate can be useful, but do not compare it as though it were the same as a detailed fixed-price quotation for a defined scope.

Compare the work item by item

Create a simple comparison sheet with the builders as columns and the same work packages as rows. Mark each item included, excluded, allowed for or unclear. Ask for a written answer to every unclear item before ranking prices. The point is to see what each total actually buys.

  • Preparation: surveys, demolition, protection of the occupied home, skip hire and lawful waste removal.
  • Structure: foundations, excavation, steel, walls, floors, roof and any temporary support.
  • Services: plumbing, electrics, heating, ventilation, drainage alterations and testing.
  • Envelope: glazing, doors, insulation, waterproofing, render and external finishes.
  • Internal finish: plastering, joinery, tiling, flooring, painting, kitchen or bathroom fitting.
  • Completion: making good, commissioning, certificates, snagging and site clearance.

For a kitchen extension, ask separately whether the kitchen units and appliances are supplied, installed, connected and decorated around. For a bathroom, distinguish sanitaryware from waterproofing, tiling, ventilation and disposal of the old fittings. The same headline room name can cover very different work.

Understand allowances and provisional sums

An allowance is an amount included for an item whose final choice is not known. A provisional sum is an estimate for work whose extent may not yet be defined. Both can move the final price. Ask what quantity, unit price, labour and VAT have been allowed, what happens if the real cost differs, and whether the builder adds a margin when the amount changes.

For example, a low allowance for floor finishes can make one quote look cheaper although your chosen material will exceed it. Likewise, excavation beside an older house may reveal unexpected ground conditions. Ask which uncertainties can be investigated before signing, and hold a project contingency separately from the contractor's quoted price.

Confirm the actual price and tax treatment

Ask whether the total includes VAT and whether the figure is a fixed quote, an estimate, a day-rate arrangement or a price with adjustable elements. Confirm which materials are included, which you must supply and whether delivery, plant hire, disposal, travel or specialist subcontractors are extra. The CCPC notes that traders must give clear pre-contract price information, including the total price inclusive of VAT or the method used to calculate it when the total cannot be determined in advance.[2]

Make each builder show the same base scope and list optional upgrades separately. That makes it easier to remove a feature without losing track of what the core project costs. Ask how any requested change will be described, priced, authorised and added to the programme before it is carried out.

Check the business and its recent work

Verify who you are contracting with: trading name, business contact details and who will manage the site. Ask for recent projects similar in size and type, and speak to references about communication, changes, workmanship and completion, not only whether they liked the finished room. Ask which trades are subcontracted and who remains responsible for their work.[1]

  • Request evidence of the insurance appropriate to the job and confirm it covers the planned work and project period.
  • For regulated electrical or gas work, confirm that the appropriate registered professional will carry it out.
  • Ask who provides design, engineering, building-control submissions, inspections and completion documents.
  • Check whether a previous customer would allow you to see a completed comparable project, where appropriate.

For extensions, the homeowner and engaged designer or builder share important building-compliance responsibilities. Clarify who owns each task in writing. A low construction price is not a saving if essential design, testing or certification is left for you to arrange later.[3]

Read the programme and payment schedule

A credible programme should explain the likely start window, overall duration, dependencies and who is on site during key phases. Ask whether the quote allows for lead times on windows, steel, kitchen components and specialist trades. Clarify what happens when weather, hidden defects or a homeowner change affects the sequence.

The CCPC advises agreeing written price, completion date, payment structure and detailed work description before paying a deposit. It cautions against large upfront payments and notes that larger projects commonly use staged payments. Tie each stage to observable work or agreed materials, keep payment records and leave a clearly defined final amount for completion and snagging.[1]

  • What triggers the deposit and is it refundable if the project does not proceed?
  • Which completed milestones trigger later invoices?
  • Who approves a variation, and how is its price and time impact recorded?
  • What is the procedure for defects, snagging, delayed completion and disputes?

Compare risk as well as cost

After the clarifications, calculate a like-for-like total: base quote plus known excluded work and realistic allowances for items you actually intend to choose. Separately note uncertainties that no builder can yet price. A quote can be attractive for good reasons, such as a suitable crew and efficient sequence, but ask for an explanation when it is far below the others.

Do not choose solely from testimonials on a platform. Use them as one signal alongside references, a site visit, the written scope and the builder's answers to technical questions. Keep all versions of quotes and written clarifications together so the final contract refers to the version everyone agreed.

A sample request for comparable quotes

'We want written quotes for a rear kitchen and dining extension to a semi-detached house in Cork. Planning status is being confirmed. The same dated drawings, finish schedule and site photographs are attached to this request. Please identify your inclusions and exclusions for demolition, foundations, steel, roof, glazing, insulation, drainage, plumbing, electrics, plastering, flooring, kitchen installation, decoration, waste removal and making good. List provisional sums separately, state whether VAT is included, and explain your programme, insurance, payment milestones and recent similar work. The house will remain occupied during construction.'

If the drawings are still conceptual, say so and ask first what information each builder needs before a firm price is possible. Update the brief once the design is settled, and ask every shortlisted builder to price the same final revision.

Frequently asked questions

How many builders' quotes should I get in Ireland?+

Seek multiple written quotes for a significant project and give every builder the same drawings and specification. Compare scope and references as well as the total price.[1]

What is the difference between a quote and an estimate?+

A quote is a stated price for defined work, subject to its written terms; an estimate is an informed prediction that can change as the scope becomes clear. Ask which parts of any offered price can change and why.

Should a builders' quote include VAT?+

Ask for the total payable and clear VAT treatment in writing. Irish consumer guidance says traders should give the total price inclusive of VAT or explain how it will be calculated if it cannot yet be fixed.[2]

What is a provisional sum in a building quote?+

It is an allowance for work that cannot yet be fully specified or priced. Ask what assumptions support it and how the final amount, labour, margin and VAT will be handled.

Should I pay the full building price upfront?+

The CCPC advises caution with large upfront payments. Agree written payment stages and keep a record of each payment; avoid paying the full cost before completion.[1]

Ready to describe your project?

Tell us about your building & extensions job and compare free quotes from interested local professionals.

Get free quotes

Related guides

Building & Extensions

House extension planning permission in Ireland: what to check first

Read
Building & Construction

How much does a house extension cost in Ireland?

Read
Carpentry & Joinery

How much does a new kitchen cost in Ireland?

Read