Electrical

Connecting electricity to a new build in Ireland: costs and checklist

Updated 11 min read

A new house needs more than an electrician to fit sockets. The network must be connected, the installation must be designed and certified, and the home must be registered with an electricity supplier. These are linked steps but they are not one price. Confusing the ESB Networks connection charge with a builder's or electrician's quote is an easy way to under-budget a self-build.

As checked on 22 September 2026, ESB Networks lists a typical charge of €3,602 for a single standard domestic connection and €4,877 for a single enhanced 16 kVA connection. These are its published typical network charges, not a guaranteed quote or the total cost of wiring a new house. Your application and site conditions determine the actual offer.[1]

This guide is for a single home on a new site. A house in a multi-unit development follows a different arrangement, and a change to an existing supply is a different application. Start with the correct route before budgeting or hiring trades.[1][2]

Which costs are you actually paying for?

Think of the project as three budgets. First is the ESB Networks connection offer for bringing a suitable supply to the premises. Second is site preparation required under the connection design, such as the specified duct, cabinet, trench or other customer-side works. Third is the registered electrical contractor's work inside the house and on the customer installation: consumer unit, circuits, wiring, outlets, fixtures, testing and certification. Your builder's contract may cover some of the second and third budgets, but do not assume it does.[1][3]

  • Ask the builder who supplies and installs the meter cabinet and ducting to the network specification.
  • Ask the electrician which circuits, devices, fittings, data points and external supplies are included.
  • Ask whether trenching, reinstatement, road or boundary works and unusual network works are included or separate.
  • Check whether prices include VAT and whether provisional allowances can change after the final design.

There is no reliable single national 'all-in connection price' for every new build. The published network charge is a starting point; the wiring design and the physical route can vary dramatically. Obtain the ESB Networks offer and written trade quotes for the same plans before treating a budget as final.[1]

When to apply and what to prepare

ESB Networks advises applying as soon as possible once planning permission is in place. For a single-site domestic connection, its application asks for a site plan with the building marked, an Ordnance Survey location map, accurate coordinates and load/connection-capacity details. Get your builder or designer to supply the drawings and ask your electrical contractor to help with capacity and heavy loads. Do not guess at the load if the design includes a heat pump, EV charging or other substantial demand.[1][2]

  • Planning and site documentation ready, with the proposed building and access clearly shown.
  • A decision on heating, hot water, cooking, EV charging and possible future loads.
  • The proposed position of the meter cabinet and a feasible route for ducts and cables.
  • One named person responsible for the application and for responding to ESB Networks requests.

If you are buying a house in a development rather than building a single home, check with the developer. ESB Networks says the overall connection charge is usually applied to the builder and incorporated in the sale price, though exceptions can arise.[4]

Understand the quoted timeline, not just the date you apply

ESB Networks says it aims to issue a quote within 15 business days and, after acceptance and payment, aims to complete a new connection within 60 business days. These are targets, not a promise that every site will be energised on that date. Wayleaves, road-opening permissions, network reinforcement, missing ducts or an outstanding wiring certificate can delay the work.[1][3]

Build the connection into the construction programme early. Ask your builder when the cabinet, duct and any trench will be ready. Ask your electrician when the installation can be tested and certified. Track the application and identify who will respond if ESB Networks puts it on hold. Temporary site power and the permanent domestic connection should be planned as separate needs if your build requires both.[3]

Why a registered electrical contractor matters

ESB Networks explains that a registered electrical contractor must test and certify a new installation. Where a completion certificate is required, the contractor's regulatory body must send a validated certificate to ESB Networks before connection work can begin. The homeowner should also receive a copy and keep it with the house records.[5]

Before accepting an electrical quote, ask who is responsible for certification, what work is included, and how changes to the agreed design will be priced. A quotation for 'first fix electrics' is not the same as a complete installed, tested and certified system. Coordinate the electrician with the builder so plastering, insulation and final finishes are not completed before cable routes are agreed.

What to ask an electrician to price

  • Floor plans with room uses, socket and lighting positions, appliance list and any outdoor points.
  • Heat-pump, immersion, cooker, EV charger and solar-ready requirements, if relevant to this design.
  • Consumer-unit specification, protective devices, earthing, testing and certification.
  • Meter-cabinet and duct interface: state whether the builder or electrician handles each part.
  • Included fittings versus owner-supplied fittings, installation of data/network cabling and smart-home items.
  • First-fix and second-fix dates, access requirements, defects process and final documentation.

Give every contractor the same drawings and schedule. Ask for a written list of exclusions and provisional sums, not simply a total. If the electrician recommends a different connection capacity, understand why before the ESB Networks application is submitted or amended. A cheaper electrical quote that omits fittings, outdoor work or certification may not be cheaper in the end.

A practical request for a new-build electrician

'We are building a single new home in County Galway and preparing an ESB Networks domestic connection application. The house will have a heat pump, electric cooking and provision for a future EV charger. Planning permission and current floor plans are available. Please quote for the complete electrical installation, including your recommended load/capacity information for the application, consumer unit, specified circuits and fittings, testing and completion certificate. State whether meter-cabinet and duct coordination, outdoor sockets and data cabling are included. The builder will handle groundworks unless agreed otherwise. Please list assumptions, VAT and your likely first-fix availability.'

The homeowner still applies through the proper ESB Networks process. HomePros can help you describe and compare the contractor-side electrical work; it does not replace the network operator or the certifying electrician.

Frequently asked questions

How much does ESB Networks charge to connect a new house in Ireland?+

As checked on 22 September 2026, ESB Networks publishes typical charges of €3,602 for a single standard domestic connection and €4,877 for an enhanced 16 kVA connection. Your actual connection offer may differ, and house wiring and site works are separate costs.[1]

Does the ESB Networks charge include wiring the house?+

Do not assume it does. The network connection offer and the registered electrician's on-site installation are different scopes. Check any builder's contract for ducting, cabinet and trench responsibilities too.[1][5]

When should I apply for a new-build connection?+

ESB Networks advises applying once planning permission is in place and as soon as possible. Allow time for the quotation, payment, site readiness and electrical certification before expecting the supply to go live.[2][3]

Who certifies the electrical installation?+

A registered electrical contractor tests and certifies it. Where required, the regulatory body sends a validated completion certificate to ESB Networks; keep your own copy of the certificate.[5]

Ready to describe your project?

Tell us about your electrical job and compare free quotes from interested local professionals.

Get free quotes

Related guides

Electrical

How much does an electrician cost in Ireland?

Read
Electrical

House rewiring cost in Ireland

Read
Building & Extensions

How to compare builders' quotes in Ireland

Read